Milestone Map: QuoteNo: Q12045 / ProdNo: 1109744
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
4/5/2024
4/30/2024
Initial Quote Receipt & Review
Darren Zielke
Final Quote Review
5/6/2024
5/3/2024
Final Quote Review
Darren Zielke
Contract Review
2/11/2025
Contract Review
Darren Zielke
Order Entry
2/12/2025
2/12/2025
Order Entry
Darren Zielke
Eng KickOff
2/18/2025
Eng Kick Off
Financial Review
4/11/2025
3/5/2025
Financial Review
Darren Zielke
Initial Design Review
3/28/2025
3/13/2025
Initial Design Review
Darren Zielke
Long Lead Release
2/28/2025
4/11/2025
Long Lead Release Date
Drawing Package Submittal
3/19/2025
3/14/2025
Drawing Package Submittal Date
Drawing Package Approval
3/19/2025
4/11/2025
Drawing Package Approval Date
Full BOM Release
3/21/2025
7/31/2025
Full BOM Release Date
Final Design Review
4/11/2025
7/29/2025
Final Design Review
Darren Zielke
Design Completion Date
5/30/2025
7/31/2025
Design Completion Date
Shop Release
7/3/2025
7/31/2025
Shop Release
Joe Marshall
Production Complete
8/15/2025
Production Complete
Order Close Out
8/18/2025
Order Close Out
Project Wrap Up
8/29/2025
Project Wrap Up
Lessons Learned
Lessons Learned