Milestone Map: QuoteNo: Q12577 / ProdNo: 1115196


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 11/19/2024 9/25/2025 Initial Quote Receipt & Review Frank Edwards
Final Quote Review 11/21/2024 9/25/2025 Final Quote Review Frank Edwards
Contract Review 9/25/2025 Contract Review Frank Edwards
Order Entry 9/25/2025 9/25/2025 Order Entry Frank Edwards
Eng KickOff 9/26/2025 9/30/2025 Eng Kick Off Joe Marshall
Financial Review 10/3/2025 9/30/2025 Financial Review Frank Edwards
Initial Design Review 10/1/2025 9/30/2025 Initial Design Review Paul Brown
Long Lead Release 10/1/2025 9/30/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 10/3/2025 9/30/2025 Full BOM Release Date
Final Design Review 10/3/2025 9/30/2025 Final Design Review Paul Brown
Design Completion Date 10/3/2025 9/30/2025 Design Completion Date
Shop Release 10/20/2025 11/10/2025 Shop Release Paul Brown
Production Complete 10/31/2025 Production Complete
Order Close Out 11/10/2025 Order Close Out
Project Wrap Up 11/13/2025 Project Wrap Up
Lessons Learned Lessons Learned