Milestone Map: QuoteNo: Q12568 / ProdNo: 1115220


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 9/19/2025 9/19/2025 Initial Quote Receipt & Review Frank Edwards
Final Quote Review 9/19/2025 9/19/2025 Final Quote Review Joe Marshall
Contract Review 9/26/2025 Contract Review Joe Marshall
Order Entry 9/26/2025 9/25/2025 Order Entry Frank Edwards
Eng KickOff 9/29/2025 10/13/2025 Eng Kick Off
Financial Review 10/13/2025 Financial Review Darren Zielke
Initial Design Review 10/3/2025 10/13/2025 Initial Design Review Darren Zielke
Long Lead Release 9/25/2025 9/25/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 10/3/2025 10/2/2025 Full BOM Release Date
Final Design Review 10/13/2025 Final Design Review Darren Zielke
Design Completion Date 10/6/2025 10/2/2025 Design Completion Date
Shop Release 10/8/2025 10/13/2025 Shop Release Darren Zielke
Production Complete 10/17/2025 Production Complete
Order Close Out 10/27/2025 Order Close Out
Project Wrap Up 10/29/2025 Project Wrap Up
Lessons Learned 10/31/2025 Lessons Learned