Milestone Map: QuoteNo: Q12564 / ProdNo: 1115089


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 9/18/2025 9/19/2025 Initial Quote Receipt & Review Frank Edwards
Final Quote Review 9/18/2025 9/19/2025 Final Quote Review Frank Edwards
Contract Review 9/19/2025 9/19/2025 Contract Review Frank Edwards
Order Entry 9/22/2025 9/19/2025 Order Entry Frank Edwards
Eng KickOff 9/23/2025 9/23/2025 Eng Kick Off Phil Kimberlin
Financial Review Financial Review
Initial Design Review 9/26/2025 Initial Design Review Phil Kimberlin
Long Lead Release 9/19/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 9/26/2025 10/13/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 9/26/2025 10/13/2025 Design Completion Date
Shop Release 10/20/2025 10/14/2025 Shop Release Phil Kimberlin
Production Complete 11/18/2025 Production Complete
Order Close Out Order Close Out
Project Wrap Up Project Wrap Up
Lessons Learned Lessons Learned