Milestone Map: QuoteNo: Q12561 / ProdNo: 1115030


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 9/15/2025 9/17/2025 Initial Quote Receipt & Review Frank Edwards
Final Quote Review 9/15/2025 9/17/2025 Final Quote Review Frank Edwards
Contract Review 9/17/2025 Contract Review Frank Edwards
Order Entry 9/18/2025 9/18/2025 Order Entry Frank Edwards
Eng KickOff 9/19/2025 9/23/2025 Eng Kick Off Phil Kimberlin
Financial Review Financial Review
Initial Design Review 9/25/2025 Initial Design Review Phil Kimberlin
Long Lead Release 9/17/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 9/19/2025 9/25/2025 Full BOM Release Date
Final Design Review 9/25/2025 Final Design Review Phil Kimberlin
Design Completion Date 9/25/2025 Design Completion Date
Shop Release 10/13/2025 10/6/2025 Shop Release Phil Kimberlin
Production Complete 10/20/2025 Production Complete
Order Close Out 10/24/2025 Order Close Out
Project Wrap Up 10/27/2025 Project Wrap Up
Lessons Learned Lessons Learned