Milestone Map: QuoteNo: Q12554 / ProdNo: 1115366


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 9/18/2025 9/19/2025 Initial Quote Receipt & Review Derrick Herr
Final Quote Review 9/24/2025 9/24/2025 Final Quote Review Derrick Herr
Contract Review 9/25/2025 Contract Review Frank Edwards
Order Entry 9/25/2025 9/25/2025 Order Entry Frank Edwards
Eng KickOff 9/29/2025 10/2/2025 Eng Kick Off Paul Brown
Financial Review 10/8/2025 10/8/2025 Financial Review Frank Edwards
Initial Design Review 10/14/2025 10/14/2025 Initial Design Review Joe Marshall
Long Lead Release 10/2/2025 10/10/2025 Long Lead Release Date
Drawing Package Submittal 10/23/2025 Drawing Package Submittal Date
Drawing Package Approval 10/28/2025 Drawing Package Approval Date
Full BOM Release 10/10/2025 11/7/2025 Full BOM Release Date
Final Design Review 10/21/2025 Final Design Review
Design Completion Date 10/17/2025 Design Completion Date
Shop Release 11/17/2025 Shop Release
Production Complete 12/3/2025 Production Complete
Order Close Out 12/8/2025 Order Close Out
Project Wrap Up 12/10/2025 Project Wrap Up
Lessons Learned 12/17/2025 Lessons Learned