Milestone Map: QuoteNo: Q12549 / ProdNo: 1115204
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
9/16/2025
9/18/2025
Initial Quote Receipt & Review
Derrick Herr
Final Quote Review
9/19/2025
9/23/2025
Final Quote Review
Frank Edwards
Contract Review
9/25/2025
Contract Review
Frank Edwards
Order Entry
9/25/2025
9/25/2025
Order Entry
Frank Edwards
Eng KickOff
9/29/2025
10/2/2025
Eng Kick Off
Paul Brown
Financial Review
10/8/2025
10/8/2025
Financial Review
Frank Edwards
Initial Design Review
10/14/2025
10/14/2025
Initial Design Review
Joe Marshall
Long Lead Release
10/2/2025
10/9/2025
Long Lead Release Date
Drawing Package Submittal
10/17/2025
Drawing Package Submittal Date
Drawing Package Approval
10/22/2025
Drawing Package Approval Date
Full BOM Release
10/10/2025
10/9/2025
Full BOM Release Date
Final Design Review
10/21/2025
Final Design Review
Design Completion Date
10/17/2025
Design Completion Date
Shop Release
11/17/2025
Shop Release
Production Complete
Production Complete
Order Close Out
12/8/2025
Order Close Out
Project Wrap Up
12/10/2025
Project Wrap Up
Lessons Learned
12/17/2025
Lessons Learned