Milestone Map: QuoteNo: Q12546 / ProdNo: 1115363


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 9/15/2025 9/15/2025 Initial Quote Receipt & Review Derrick Herr
Final Quote Review 9/16/2025 9/22/2025 Final Quote Review Joe Marshall
Contract Review 9/26/2025 Contract Review Frank Edwards
Order Entry 9/26/2025 9/26/2025 Order Entry Frank Edwards
Eng KickOff 9/30/2025 10/2/2025 Eng Kick Off Paul Brown
Financial Review 10/24/2025 10/6/2025 Financial Review Frank Edwards
Initial Design Review 10/10/2025 10/14/2025 Initial Design Review Joe Marshall
Long Lead Release 10/3/2025 10/6/2025 Long Lead Release Date
Drawing Package Submittal 10/13/2025 10/14/2025 Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 10/31/2025 10/6/2025 Full BOM Release Date
Final Design Review 10/24/2025 10/23/2025 Final Design Review Paul Brown
Design Completion Date 10/31/2025 10/22/2025 Design Completion Date
Shop Release 1/12/2026 Shop Release
Production Complete 2/2/2026 Production Complete
Order Close Out 2/11/2026 Order Close Out
Project Wrap Up 2/13/2026 Project Wrap Up
Lessons Learned 2/18/2026 Lessons Learned