Milestone Map: QuoteNo: Q12539 / ProdNo: 1116078
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
9/11/2025
9/11/2025
Initial Quote Receipt & Review
Joe Marshall
Final Quote Review
9/24/2025
10/30/2025
Final Quote Review
Frank Edwards
Contract Review
10/30/2025
Contract Review
Frank Edwards
Order Entry
10/30/2025
10/30/2025
Order Entry
Frank Edwards
Eng KickOff
11/3/2025
11/5/2025
Eng Kick Off
Phil Kimberlin
Financial Review
Financial Review
Initial Design Review
12/19/2025
11/11/2025
Initial Design Review
Phil Kimberlin
Long Lead Release
Long Lead Release Date
Drawing Package Submittal
Drawing Package Submittal Date
Drawing Package Approval
Drawing Package Approval Date
Full BOM Release
10/30/2025
10/30/2025
Full BOM Release Date
Final Design Review
12/19/2025
11/11/2025
Final Design Review
Phil Kimberlin
Design Completion Date
12/19/2025
11/11/2025
Design Completion Date
Shop Release
1/5/2026
Shop Release
Production Complete
1/14/2026
Production Complete
Order Close Out
1/20/2026
Order Close Out
Project Wrap Up
1/22/2026
Project Wrap Up
Lessons Learned
Lessons Learned