Milestone Map: QuoteNo: Q12019 / ProdNo: 1114834


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 6/20/2025 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 6/20/2025 Final Quote Review Joe Marshall
Contract Review 9/2/2025 Contract Review Joe Marshall
Order Entry 9/3/2025 9/3/2025 Order Entry Joe Marshall
Eng KickOff 9/9/2025 9/15/2025 Eng Kick Off Joe Marshall
Financial Review Financial Review
Initial Design Review Initial Design Review
Long Lead Release 9/3/2025 9/3/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 9/11/2025 9/5/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 9/12/2025 9/23/2025 Design Completion Date
Shop Release 9/29/2025 9/30/2025 Shop Release Phil Kimberlin
Production Complete 11/6/2025 Production Complete
Order Close Out 11/10/2025 Order Close Out
Project Wrap Up 11/14/2025 Project Wrap Up
Lessons Learned Lessons Learned