Milestone Map: QuoteNo: Q12019 / ProdNo: 1114834
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
6/20/2025
Initial Quote Receipt & Review
Joe Marshall
Final Quote Review
6/20/2025
Final Quote Review
Joe Marshall
Contract Review
9/2/2025
Contract Review
Joe Marshall
Order Entry
9/3/2025
9/3/2025
Order Entry
Joe Marshall
Eng KickOff
9/9/2025
9/15/2025
Eng Kick Off
Joe Marshall
Financial Review
Financial Review
Initial Design Review
Initial Design Review
Long Lead Release
9/3/2025
9/3/2025
Long Lead Release Date
Drawing Package Submittal
Drawing Package Submittal Date
Drawing Package Approval
Drawing Package Approval Date
Full BOM Release
9/11/2025
9/5/2025
Full BOM Release Date
Final Design Review
Final Design Review
Design Completion Date
9/12/2025
9/23/2025
Design Completion Date
Shop Release
9/29/2025
9/30/2025
Shop Release
Phil Kimberlin
Production Complete
11/6/2025
Production Complete
Order Close Out
11/10/2025
Order Close Out
Project Wrap Up
11/14/2025
Project Wrap Up
Lessons Learned
Lessons Learned