Milestone Map: QuoteNo: Q12531 / ProdNo: 1115372


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 9/8/2025 9/10/2025 Initial Quote Receipt & Review Derrick Herr
Final Quote Review 9/11/2025 9/16/2025 Final Quote Review Joe Marshall
Contract Review 9/30/2025 Contract Review Frank Edwards
Order Entry 9/30/2025 9/30/2025 Order Entry Frank Edwards
Eng KickOff 10/3/2025 10/3/2025 Eng Kick Off Dylan Smith
Financial Review 10/13/2025 10/21/2025 Financial Review Frank Edwards
Initial Design Review 10/10/2025 10/15/2025 Initial Design Review Dylan Smith
Long Lead Release 9/30/2025 9/30/2025 Long Lead Release Date
Drawing Package Submittal 10/24/2025 Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 10/10/2025 10/22/2025 Full BOM Release Date
Final Design Review 10/13/2025 10/28/2025 Final Design Review Dylan Smith
Design Completion Date 10/10/2025 10/27/2025 Design Completion Date
Shop Release 11/3/2025 Shop Release
Production Complete 11/19/2025 Production Complete
Order Close Out 11/24/2025 Order Close Out
Project Wrap Up 11/26/2025 Project Wrap Up
Lessons Learned 12/3/2025 Lessons Learned