Milestone Map: QuoteNo: Q12531 / ProdNo: 1115372
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
9/8/2025
9/10/2025
Initial Quote Receipt & Review
Derrick Herr
Final Quote Review
9/11/2025
9/16/2025
Final Quote Review
Joe Marshall
Contract Review
9/30/2025
Contract Review
Frank Edwards
Order Entry
9/30/2025
9/30/2025
Order Entry
Frank Edwards
Eng KickOff
10/3/2025
10/3/2025
Eng Kick Off
Dylan Smith
Financial Review
10/13/2025
10/21/2025
Financial Review
Frank Edwards
Initial Design Review
10/10/2025
10/15/2025
Initial Design Review
Dylan Smith
Long Lead Release
9/30/2025
9/30/2025
Long Lead Release Date
Drawing Package Submittal
10/24/2025
Drawing Package Submittal Date
Drawing Package Approval
Drawing Package Approval Date
Full BOM Release
10/10/2025
10/22/2025
Full BOM Release Date
Final Design Review
10/13/2025
10/28/2025
Final Design Review
Dylan Smith
Design Completion Date
10/10/2025
10/27/2025
Design Completion Date
Shop Release
11/3/2025
Shop Release
Production Complete
11/19/2025
Production Complete
Order Close Out
11/24/2025
Order Close Out
Project Wrap Up
11/26/2025
Project Wrap Up
Lessons Learned
12/3/2025
Lessons Learned