Milestone Map: QuoteNo: Q12501 / ProdNo: 1114747


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 8/18/2025 8/19/2025 Initial Quote Receipt & Review
Final Quote Review 8/20/2025 8/20/2025 Final Quote Review Joe Marshall
Contract Review 9/4/2025 Contract Review Joe Marshall
Order Entry 9/3/2025 9/5/2025 Order Entry Joe Marshall
Eng KickOff 9/8/2025 9/11/2025 Eng Kick Off Dylan Smith
Financial Review Financial Review
Initial Design Review Initial Design Review
Long Lead Release Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 9/4/2025 9/4/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 10/3/2025 9/25/2025 Design Completion Date
Shop Release 11/10/2025 11/14/2025 Shop Release Dylan Smith
Production Complete 1/28/2026 Production Complete
Order Close Out 1/30/2026 Order Close Out
Project Wrap Up 2/6/2026 Project Wrap Up
Lessons Learned Lessons Learned