Initial Quote Receipt & Review 8/1/2025 8/5/2025 Initial Quote Receipt & Review
Final Quote Review 8/1/2025 8/18/2025 Final Quote Review Joe Marshall
Contract Review 8/29/2025 Contract Review Joe Marshall
Order Entry 8/27/2025 8/29/2025 Order Entry Joe Marshall
Eng KickOff 9/2/2025 9/4/2025 Eng Kick Off Dylan Smith
Financial Review Financial Review
Initial Design Review Initial Design Review
Long Lead Release 8/29/2025 8/26/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 8/29/2025 8/26/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 8/29/2025 8/26/2025 Design Completion Date
Shop Release 9/3/2025 9/12/2025 Shop Release Dylan Smith
Production Complete 9/19/2025 10/8/2025 Production Complete
Order Close Out 9/26/2025 Order Close Out
Project Wrap Up 10/1/2025 Project Wrap Up