Milestone Map: QuoteNo: Q12516 / ProdNo: 1115213


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 8/27/2025 8/28/2025 Initial Quote Receipt & Review Scott Tidwell
Final Quote Review 8/28/2025 9/8/2025 Final Quote Review Joe Marshall
Contract Review 9/25/2025 Contract Review Joe Marshall
Order Entry 9/25/2025 9/25/2025 Order Entry Joe Marshall
Eng KickOff 9/30/2025 9/29/2025 Eng Kick Off Scott Tidwell
Financial Review Financial Review
Initial Design Review 9/30/2025 Initial Design Review Scott Tidwell
Long Lead Release 10/1/2025 9/30/2025 Long Lead Release Date
Drawing Package Submittal 9/30/2025 Drawing Package Submittal Date
Drawing Package Approval 11/6/2025 Drawing Package Approval Date
Full BOM Release 10/10/2025 10/3/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 10/13/2025 10/3/2025 Design Completion Date
Shop Release 12/2/2025 Shop Release
Production Complete 12/18/2025 Production Complete
Order Close Out 12/22/2025 Order Close Out
Project Wrap Up 1/9/2026 Project Wrap Up
Lessons Learned Lessons Learned