Milestone Map: QuoteNo: Q12507 / ProdNo: 1114558


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 8/21/2025 8/21/2025 Initial Quote Receipt & Review Scott Tidwell
Final Quote Review 8/26/2025 8/22/2025 Final Quote Review Joe Marshall
Contract Review 9/4/2025 Contract Review Joe Marshall
Order Entry 9/4/2025 9/5/2025 Order Entry Joe Marshall
Eng KickOff 9/9/2025 9/9/2025 Eng Kick Off Scott Tidwell
Financial Review Financial Review
Initial Design Review 9/9/2025 Initial Design Review Scott Tidwell
Long Lead Release 9/12/2025 9/9/2025 Long Lead Release Date
Drawing Package Submittal 9/9/2025 Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 9/17/2025 9/9/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 9/18/2025 9/9/2025 Design Completion Date
Shop Release 10/24/2025 10/23/2025 Shop Release Scott Tidwell
Production Complete 11/19/2025 Production Complete
Order Close Out 11/21/2025 Order Close Out
Project Wrap Up 12/5/2025 Project Wrap Up
Lessons Learned Lessons Learned