Milestone Map: QuoteNo: Q12202 / ProdNo: 1114184


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 1/13/2025 8/15/2025 Initial Quote Receipt & Review Frank Edwards
Final Quote Review 1/14/2025 8/15/2025 Final Quote Review Frank Edwards
Contract Review 8/15/2025 Contract Review Frank Edwards
Order Entry 8/15/2025 8/15/2025 Order Entry Frank Edwards
Eng KickOff 8/15/2025 8/15/2025 Eng Kick Off Frank Edwards
Financial Review 8/15/2025 8/15/2025 Financial Review Frank Edwards
Initial Design Review 8/15/2025 8/15/2025 Initial Design Review Frank Edwards
Long Lead Release 8/15/2025 8/15/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 8/15/2025 8/21/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 8/29/2025 8/21/2025 Design Completion Date
Shop Release 9/2/2025 9/15/2025 Shop Release Joe Marshall
Production Complete 8/25/2025 9/24/2025 Production Complete
Order Close Out 9/16/2025 10/3/2025 Order Close Out Noelle Sorano
Project Wrap Up 9/17/2025 10/3/2025 Project Wrap Up
Lessons Learned Lessons Learned