Milestone Map: QuoteNo: Q12489 / ProdNo: 1114151


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 8/12/2025 8/12/2025 Initial Quote Receipt & Review Frank Edwards
Final Quote Review 8/12/2025 8/12/2025 Final Quote Review Frank Edwards
Contract Review 8/14/2025 Contract Review Frank Edwards
Order Entry 8/14/2025 8/14/2025 Order Entry Joe Marshall
Eng KickOff 8/14/2025 8/14/2025 Eng Kick Off Frank Edwards
Financial Review 8/15/2025 8/28/2025 Financial Review Dylan Smith
Initial Design Review 8/14/2025 8/14/2025 Initial Design Review Frank Edwards
Long Lead Release 8/14/2025 8/14/2025 Long Lead Release Date
Drawing Package Submittal 8/14/2025 8/14/2025 Drawing Package Submittal Date
Drawing Package Approval 8/14/2025 8/14/2025 Drawing Package Approval Date
Full BOM Release 8/14/2025 8/14/2025 Full BOM Release Date
Final Design Review 8/15/2025 8/14/2025 Final Design Review Frank Edwards
Design Completion Date 8/14/2025 8/14/2025 Design Completion Date
Shop Release 8/14/2025 8/21/2025 Shop Release Dylan Smith
Production Complete 8/25/2025 9/3/2025 Production Complete
Order Close Out 8/28/2025 9/24/2025 Order Close Out Noelle Sorano
Project Wrap Up 8/29/2025 9/26/2025 Project Wrap Up
Lessons Learned Lessons Learned