Milestone Map: QuoteNo: Q12484 / ProdNo: 1114650


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 8/8/2025 8/12/2025 Initial Quote Receipt & Review Scott Tidwell
Final Quote Review 8/12/2025 8/12/2025 Final Quote Review Joe Marshall
Contract Review 9/5/2025 Contract Review Joe Marshall
Order Entry 8/29/2025 9/5/2025 Order Entry Joe Marshall
Eng KickOff 9/8/2025 9/17/2025 Eng Kick Off Darren Zielke
Financial Review 9/24/2025 Financial Review Darren Zielke
Initial Design Review 9/24/2025 Initial Design Review Darren Zielke
Long Lead Release 9/4/2025 9/4/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 9/4/2025 9/4/2025 Full BOM Release Date
Final Design Review 9/24/2025 Final Design Review Darren Zielke
Design Completion Date 9/19/2025 9/24/2025 Design Completion Date
Shop Release 11/3/2025 9/24/2025 Shop Release Darren Zielke
Production Complete 11/13/2025 Production Complete
Order Close Out 11/14/2025 Order Close Out
Project Wrap Up 11/21/2025 Project Wrap Up
Lessons Learned Lessons Learned