Milestone Map: QuoteNo: Q12482 / ProdNo: 1115653


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 8/7/2025 8/7/2025 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 8/7/2025 8/7/2025 Final Quote Review Joe Marshall
Contract Review 10/15/2025 Contract Review Joe Marshall
Order Entry 10/15/2025 10/15/2025 Order Entry Joe Marshall
Eng KickOff 10/16/2025 10/21/2025 Eng Kick Off
Financial Review 10/22/2025 10/21/2025 Financial Review Joe Marshall
Initial Design Review Initial Design Review
Long Lead Release 10/17/2025 10/23/2025 Long Lead Release Date
Drawing Package Submittal 11/7/2025 11/5/2025 Drawing Package Submittal Date
Drawing Package Approval 11/14/2025 Drawing Package Approval Date
Full BOM Release 10/24/2025 10/23/2025 Full BOM Release Date
Final Design Review 10/22/2025 10/28/2025 Final Design Review Joe Marshall
Design Completion Date 12/3/2025 11/4/2025 Design Completion Date
Shop Release 12/11/2025 Shop Release
Production Complete 12/19/2025 Production Complete
Order Close Out 12/22/2025 Order Close Out
Project Wrap Up 1/7/2026 Project Wrap Up
Lessons Learned Lessons Learned