Milestone Map: QuoteNo: Q12403 / ProdNo: 1113902


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 8/4/2025 8/5/2025 Initial Quote Receipt & Review Frank Edwards
Final Quote Review 8/4/2025 8/5/2025 Final Quote Review Frank Edwards
Contract Review 8/5/2025 8/6/2025 Contract Review Frank Edwards
Order Entry 8/6/2025 8/5/2025 Order Entry Joe Marshall
Eng KickOff 8/8/2025 8/8/2025 Eng Kick Off Dylan Smith
Financial Review Financial Review
Initial Design Review Initial Design Review
Long Lead Release 8/5/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 8/5/2025 8/5/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 8/5/2025 8/5/2025 Design Completion Date
Shop Release 9/2/2025 9/17/2025 Shop Release Dylan Smith
Production Complete 10/15/2025 9/22/2025 Production Complete
Order Close Out 10/16/2025 9/24/2025 Order Close Out Noelle Sorano
Project Wrap Up 10/24/2025 9/26/2025 Project Wrap Up
Lessons Learned Lessons Learned