Milestone Map: QuoteNo: Q12479 / ProdNo: 1114463


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 8/6/2025 8/12/2025 Initial Quote Receipt & Review Scott Tidwell
Final Quote Review 8/6/2025 8/25/2025 Final Quote Review Joe Marshall
Contract Review 8/26/2025 Contract Review Joe Marshall
Order Entry 8/13/2025 8/26/2025 Order Entry Joe Marshall
Eng KickOff 8/27/2025 8/27/2025 Eng Kick Off Scott Tidwell
Financial Review Financial Review
Initial Design Review 8/27/2025 Initial Design Review Scott Tidwell
Long Lead Release 8/27/2025 8/27/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 8/27/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 8/27/2025 Design Completion Date
Shop Release 9/24/2025 9/9/2025 Shop Release Scott Tidwell
Production Complete Production Complete
Order Close Out 10/2/2025 Order Close Out
Project Wrap Up 10/7/2025 Project Wrap Up
Lessons Learned Lessons Learned