Milestone Map: QuoteNo: Q12475 / ProdNo: 1114182


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 8/5/2025 8/5/2025 Initial Quote Receipt & Review Derrick Herr
Final Quote Review 8/5/2025 8/6/2025 Final Quote Review Frank Edwards
Contract Review 8/14/2025 Contract Review Frank Edwards
Order Entry 8/15/2025 8/14/2025 Order Entry Frank Edwards
Eng KickOff 8/14/2025 8/14/2025 Eng Kick Off Frank Edwards
Financial Review 8/14/2025 8/14/2025 Financial Review Frank Edwards
Initial Design Review Initial Design Review
Long Lead Release 8/14/2025 8/14/2025 Long Lead Release Date
Drawing Package Submittal 8/20/2025 Drawing Package Submittal Date
Drawing Package Approval 8/21/2025 Drawing Package Approval Date
Full BOM Release 8/14/2025 8/28/2025 Full BOM Release Date
Final Design Review 9/24/2025 Final Design Review Phil Kimberlin
Design Completion Date 8/22/2025 8/28/2025 Design Completion Date
Shop Release 8/25/2025 8/28/2025 Shop Release Joe Marshall
Production Complete 9/8/2025 9/12/2025 Production Complete
Order Close Out 9/12/2025 9/24/2025 Order Close Out Noelle Sorano
Project Wrap Up 9/15/2025 9/24/2025 Project Wrap Up
Lessons Learned Lessons Learned