Milestone Map: QuoteNo: Q12471 / ProdNo: 1114225


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 8/1/2025 8/1/2025 Initial Quote Receipt & Review Derrick Herr
Final Quote Review 8/4/2025 8/1/2025 Final Quote Review Frank Edwards
Contract Review 8/15/2025 Contract Review Frank Edwards
Order Entry 8/18/2025 8/15/2025 Order Entry Frank Edwards
Eng KickOff 8/15/2025 8/15/2025 Eng Kick Off Frank Edwards
Financial Review 8/15/2025 8/15/2025 Financial Review Frank Edwards
Initial Design Review 8/15/2025 8/15/2025 Initial Design Review Frank Edwards
Long Lead Release 8/15/2025 8/15/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 8/15/2025 8/15/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 8/15/2025 8/15/2025 Design Completion Date
Shop Release 10/20/2025 9/17/2025 Shop Release Dylan Smith
Production Complete 10/27/2025 9/22/2025 Production Complete
Order Close Out 10/29/2025 9/24/2025 Order Close Out Noelle Sorano
Project Wrap Up 10/30/2025 9/26/2025 Project Wrap Up
Lessons Learned Lessons Learned