Milestone Map: QuoteNo: Q12468 / ProdNo: 1114950


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 7/31/2025 9/18/2025 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 8/5/2025 9/18/2025 Final Quote Review Joe Marshall
Contract Review 9/18/2025 Contract Review Joe Marshall
Order Entry 9/11/2025 9/18/2025 Order Entry Joe Marshall
Eng KickOff 9/16/2025 9/18/2025 Eng Kick Off Dylan Smith
Financial Review 9/22/2025 10/1/2025 Financial Review Dylan Smith
Initial Design Review Initial Design Review
Long Lead Release 9/12/2025 9/12/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 9/19/2025 9/29/2025 Full BOM Release Date
Final Design Review 9/22/2025 10/1/2025 Final Design Review Dylan Smith
Design Completion Date 9/22/2025 9/29/2025 Design Completion Date
Shop Release 10/10/2025 11/4/2025 Shop Release Dylan Smith
Production Complete 11/11/2025 Production Complete
Order Close Out 11/13/2025 Order Close Out
Project Wrap Up 11/26/2025 Project Wrap Up
Lessons Learned Lessons Learned