Milestone Map: QuoteNo: Q12465 / ProdNo: 1114419


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 8/5/2025 Initial Quote Receipt & Review Scott Tidwell
Final Quote Review 8/5/2025 Final Quote Review Scott Tidwell
Contract Review 11/10/2025 Contract Review Noelle Sorano
Order Entry 8/25/2025 8/23/2025 Order Entry Frank Edwards
Eng KickOff 8/28/2025 8/28/2025 Eng Kick Off Paul Brown
Financial Review 9/10/2025 Financial Review Frank Edwards
Initial Design Review 9/12/2025 9/9/2025 Initial Design Review Paul Brown
Long Lead Release 8/22/2025 8/22/2025 Long Lead Release Date
Drawing Package Submittal 9/12/2025 Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 8/29/2025 9/22/2025 Full BOM Release Date
Final Design Review 10/23/2025 Final Design Review Paul Brown
Design Completion Date 9/2/2025 9/22/2025 Design Completion Date
Shop Release 10/6/2025 10/28/2025 Shop Release Paul Brown
Production Complete 10/29/2025 Production Complete
Order Close Out 11/4/2025 Order Close Out
Project Wrap Up 11/7/2025 Project Wrap Up
Lessons Learned Lessons Learned