Milestone Map: QuoteNo: Q12402 / ProdNo: 1113798


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 6/13/2025 6/13/2025 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 6/19/2025 6/19/2025 Final Quote Review Joe Marshall
Contract Review 7/25/2025 Contract Review Joe Marshall
Order Entry 7/24/2025 7/28/2025 Order Entry Joe Marshall
Eng KickOff 7/31/2025 7/31/2025 Eng Kick Off Dylan Smith
Financial Review Financial Review
Initial Design Review Initial Design Review
Long Lead Release 8/6/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 7/28/2025 8/6/2025 Full BOM Release Date
Final Design Review 8/4/2025 9/16/2025 Final Design Review Dylan Smith
Design Completion Date 8/15/2025 8/6/2025 Design Completion Date
Shop Release 9/10/2025 9/16/2025 Shop Release Dylan Smith
Production Complete 10/14/2025 10/10/2025 Production Complete
Order Close Out 10/16/2025 Order Close Out
Project Wrap Up 10/22/2025 Project Wrap Up
Lessons Learned Lessons Learned