Milestone Map: QuoteNo: Q12124 / ProdNo: 1112962


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 10/28/2024 10/28/2024 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 10/31/2024 11/6/2024 Final Quote Review Joe Marshall
Contract Review 6/26/2025 6/26/2025 Contract Review Joe Marshall
Order Entry 6/27/2025 7/25/2025 Order Entry Joe Marshall
Eng KickOff 7/2/2025 7/7/2025 Eng Kick Off Dylan Smith
Financial Review 8/1/2025 8/5/2025 Financial Review Dylan Smith
Initial Design Review 7/17/2025 7/17/2025 Initial Design Review Dylan Smith
Long Lead Release 7/3/2025 7/11/2025 Long Lead Release Date
Drawing Package Submittal 7/23/2025 Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 7/11/2025 7/30/2025 Full BOM Release Date
Final Design Review 8/1/2025 7/31/2025 Final Design Review Dylan Smith
Design Completion Date 8/1/2025 9/15/2025 Design Completion Date
Shop Release 11/3/2025 10/8/2025 Shop Release Dylan Smith
Production Complete 11/24/2025 Production Complete
Order Close Out 11/26/2025 Order Close Out
Project Wrap Up 12/5/2025 Project Wrap Up
Lessons Learned 12/12/2025 Lessons Learned