Milestone Map: QuoteNo: Q12460 / ProdNo: 1113596


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 4/30/2025 7/23/2025 Initial Quote Receipt & Review Frank Edwards
Final Quote Review 4/30/2025 7/23/2025 Final Quote Review Frank Edwards
Contract Review 7/23/2025 7/23/2025 Contract Review Frank Edwards
Order Entry 7/23/2025 7/23/2025 Order Entry Frank Edwards
Eng KickOff 7/23/2025 7/23/2025 Eng Kick Off Frank Edwards
Financial Review 7/23/2025 7/23/2025 Financial Review Frank Edwards
Initial Design Review 7/23/2025 7/23/2025 Initial Design Review Frank Edwards
Long Lead Release 7/23/2025 7/23/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 7/23/2025 7/23/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 7/23/2025 7/23/2025 Design Completion Date
Shop Release 10/6/2025 9/30/2025 Shop Release Paul Brown
Production Complete Production Complete
Order Close Out 11/14/2025 Order Close Out
Project Wrap Up 11/18/2025 Project Wrap Up
Lessons Learned 11/18/2025 Lessons Learned