Milestone Map: QuoteNo: Q12455 / ProdNo: 1113913


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 7/17/2025 7/23/2025 Initial Quote Receipt & Review Scott Tidwell
Final Quote Review 7/18/2025 8/5/2025 Final Quote Review Joe Marshall
Contract Review 8/6/2025 Contract Review Frank Edwards
Order Entry 8/6/2025 8/5/2025 Order Entry Joe Marshall
Eng KickOff 8/6/2025 8/28/2025 Eng Kick Off Joe Marshall
Financial Review Financial Review
Initial Design Review 9/23/2025 Initial Design Review Phil Kimberlin
Long Lead Release 8/7/2025 8/7/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 8/12/2025 9/5/2025 Full BOM Release Date
Final Design Review 9/23/2025 Final Design Review Phil Kimberlin
Design Completion Date 8/12/2025 9/17/2025 Design Completion Date
Shop Release 9/25/2025 9/23/2025 Shop Release Phil Kimberlin
Production Complete 10/2/2025 9/22/2025 Production Complete
Order Close Out 10/6/2025 10/3/2025 Order Close Out Noelle Sorano
Project Wrap Up 10/10/2025 10/3/2025 Project Wrap Up
Lessons Learned Lessons Learned