Milestone Map: QuoteNo: Q12446 / ProdNo: 1113935


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 7/16/2025 7/16/2025 Initial Quote Receipt & Review Derrick Herr
Final Quote Review 7/16/2025 7/21/2025 Final Quote Review Derrick Herr
Contract Review 8/6/2025 Contract Review Frank Edwards
Order Entry 8/6/2025 8/6/2025 Order Entry Joe Marshall
Eng KickOff 8/6/2025 8/13/2025 Eng Kick Off Dylan Smith
Financial Review 8/15/2025 8/21/2025 Financial Review Dylan Smith
Initial Design Review 8/21/2025 8/21/2025 Initial Design Review Dylan Smith
Long Lead Release 8/6/2025 8/6/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 8/22/2025 8/20/2025 Full BOM Release Date
Final Design Review 8/15/2025 8/21/2025 Final Design Review Dylan Smith
Design Completion Date 8/22/2025 8/20/2025 Design Completion Date
Shop Release 9/15/2025 9/25/2025 Shop Release Dylan Smith
Production Complete 10/2/2025 10/8/2025 Production Complete
Order Close Out 10/6/2025 Order Close Out
Project Wrap Up 10/10/2025 10/9/2025 Project Wrap Up
Lessons Learned Lessons Learned