Milestone Map: QuoteNo: Q12430 / ProdNo: 1113276


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review Initial Quote Receipt & Review
Final Quote Review 6/12/2025 Final Quote Review Joe Marshall
Contract Review 6/13/2025 Contract Review Joe Marshall
Order Entry 6/13/2025 6/13/2025 Order Entry Joe Marshall
Eng KickOff 6/20/2025 9/22/2025 Eng Kick Off Anthony Bizon
Financial Review 7/31/2025 9/17/2025 Financial Review Frank Edwards
Initial Design Review 9/22/2025 9/22/2025 Initial Design Review Anthony Bizon
Long Lead Release 7/18/2025 8/22/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 7/31/2025 9/9/2025 Full BOM Release Date
Final Design Review 7/31/2025 9/22/2025 Final Design Review Anthony Bizon
Design Completion Date 8/22/2025 9/9/2025 Design Completion Date
Shop Release 11/10/2025 9/22/2025 Shop Release Anthony Bizon
Production Complete 11/21/2025 Production Complete
Order Close Out 11/28/2025 Order Close Out
Project Wrap Up 12/5/2025 Project Wrap Up
Lessons Learned Lessons Learned