Milestone Map: QuoteNo: Q12429 / ProdNo: 1113612


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 7/10/2025 7/9/2025 Initial Quote Receipt & Review
Final Quote Review 7/14/2025 7/14/2025 Final Quote Review Stephen English
Contract Review 7/24/2025 7/24/2025 Contract Review Frank Edwards
Order Entry 7/24/2025 7/24/2025 Order Entry Frank Edwards
Eng KickOff 7/28/2025 8/7/2025 Eng Kick Off Paul Brown
Financial Review 7/31/2025 7/24/2025 Financial Review Frank Edwards
Initial Design Review 7/30/2025 7/30/2025 Initial Design Review Paul Brown
Long Lead Release 7/24/2025 8/13/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 7/29/2025 8/13/2025 Full BOM Release Date
Final Design Review 7/31/2025 8/14/2025 Final Design Review Paul Brown
Design Completion Date 7/29/2025 9/2/2025 Design Completion Date
Shop Release 8/11/2025 9/4/2025 Shop Release Paul Brown
Production Complete 9/2/2025 9/10/2025 Production Complete
Order Close Out 9/5/2025 9/24/2025 Order Close Out Noelle Sorano
Project Wrap Up 9/8/2025 9/26/2025 Project Wrap Up
Lessons Learned 9/10/2025 Lessons Learned