Milestone Map: QuoteNo: Q12429 / ProdNo: 1113612
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
7/10/2025
7/9/2025
Initial Quote Receipt & Review
Final Quote Review
7/14/2025
7/14/2025
Final Quote Review
Stephen English
Contract Review
7/24/2025
7/24/2025
Contract Review
Frank Edwards
Order Entry
7/24/2025
7/24/2025
Order Entry
Frank Edwards
Eng KickOff
7/28/2025
8/7/2025
Eng Kick Off
Paul Brown
Financial Review
7/31/2025
7/24/2025
Financial Review
Frank Edwards
Initial Design Review
7/30/2025
7/30/2025
Initial Design Review
Paul Brown
Long Lead Release
7/24/2025
8/13/2025
Long Lead Release Date
Drawing Package Submittal
Drawing Package Submittal Date
Drawing Package Approval
Drawing Package Approval Date
Full BOM Release
7/29/2025
8/13/2025
Full BOM Release Date
Final Design Review
7/31/2025
8/14/2025
Final Design Review
Paul Brown
Design Completion Date
7/29/2025
9/2/2025
Design Completion Date
Shop Release
8/11/2025
9/4/2025
Shop Release
Paul Brown
Production Complete
9/2/2025
9/10/2025
Production Complete
Order Close Out
9/5/2025
9/24/2025
Order Close Out
Noelle Sorano
Project Wrap Up
9/8/2025
9/26/2025
Project Wrap Up
Lessons Learned
9/10/2025
Lessons Learned