Milestone Map: QuoteNo: Q12418 / ProdNo: 1112604


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 6/7/2024 6/6/2024 Initial Quote Receipt & Review
Final Quote Review 6/10/2024 6/6/2025 Final Quote Review Joe Marshall
Contract Review 6/9/2025 Contract Review Joe Marshall
Order Entry 6/9/2025 6/9/2025 Order Entry Joe Marshall
Eng KickOff 6/13/2025 6/13/2025 Eng Kick Off Dylan Smith
Financial Review Financial Review
Initial Design Review Initial Design Review
Long Lead Release 6/9/2025 Long Lead Release Date
Drawing Package Submittal 7/15/2025 Drawing Package Submittal Date
Drawing Package Approval 7/16/2025 Drawing Package Approval Date
Full BOM Release 7/17/2025 6/9/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 7/17/2025 7/16/2025 Design Completion Date
Shop Release 9/15/2025 9/19/2025 Shop Release Dylan Smith
Production Complete 10/8/2025 9/26/2025 Production Complete
Order Close Out 10/10/2025 Order Close Out
Project Wrap Up 10/17/2025 10/2/2025 Project Wrap Up
Lessons Learned 10/24/2025 Lessons Learned