Milestone Map: QuoteNo: Q12418 / ProdNo: 1112604
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
6/7/2024
6/6/2024
Initial Quote Receipt & Review
Final Quote Review
6/10/2024
6/6/2025
Final Quote Review
Joe Marshall
Contract Review
6/9/2025
Contract Review
Joe Marshall
Order Entry
6/9/2025
6/9/2025
Order Entry
Joe Marshall
Eng KickOff
6/13/2025
6/13/2025
Eng Kick Off
Dylan Smith
Financial Review
Financial Review
Initial Design Review
Initial Design Review
Long Lead Release
6/9/2025
Long Lead Release Date
Drawing Package Submittal
7/15/2025
Drawing Package Submittal Date
Drawing Package Approval
7/16/2025
Drawing Package Approval Date
Full BOM Release
7/17/2025
6/9/2025
Full BOM Release Date
Final Design Review
Final Design Review
Design Completion Date
7/17/2025
7/16/2025
Design Completion Date
Shop Release
9/15/2025
9/19/2025
Shop Release
Dylan Smith
Production Complete
10/8/2025
9/26/2025
Production Complete
Order Close Out
10/10/2025
Order Close Out
Project Wrap Up
10/17/2025
10/2/2025
Project Wrap Up
Lessons Learned
10/24/2025
Lessons Learned