Milestone Map: QuoteNo: Q12415 / ProdNo: 1115788


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 8/14/2025 8/14/2025 Initial Quote Receipt & Review Stephen English
Final Quote Review 8/20/2025 10/15/2025 Final Quote Review Joe Marshall
Contract Review 10/17/2025 Contract Review Frank Edwards
Order Entry 10/20/2025 10/17/2025 Order Entry Frank Edwards
Eng KickOff 10/21/2025 11/4/2025 Eng Kick Off Dylan Smith
Financial Review 10/31/2025 Financial Review
Initial Design Review 11/7/2025 Initial Design Review
Long Lead Release 10/31/2025 Long Lead Release Date
Drawing Package Submittal 11/14/2025 Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 12/1/2025 Full BOM Release Date
Final Design Review 12/1/2025 Final Design Review
Design Completion Date 12/1/2025 Design Completion Date
Shop Release 2/2/2026 Shop Release
Production Complete 3/25/2026 Production Complete
Order Close Out 4/2/2026 Order Close Out
Project Wrap Up 4/9/2026 Project Wrap Up
Lessons Learned 4/14/2026 Lessons Learned