Milestone Map: QuoteNo: Q12415 / ProdNo: 1115788
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
8/14/2025
8/14/2025
Initial Quote Receipt & Review
Stephen English
Final Quote Review
8/20/2025
10/15/2025
Final Quote Review
Joe Marshall
Contract Review
10/17/2025
Contract Review
Frank Edwards
Order Entry
10/20/2025
10/17/2025
Order Entry
Frank Edwards
Eng KickOff
10/21/2025
11/4/2025
Eng Kick Off
Dylan Smith
Financial Review
10/31/2025
Financial Review
Initial Design Review
11/7/2025
Initial Design Review
Long Lead Release
10/31/2025
Long Lead Release Date
Drawing Package Submittal
11/14/2025
Drawing Package Submittal Date
Drawing Package Approval
Drawing Package Approval Date
Full BOM Release
12/1/2025
Full BOM Release Date
Final Design Review
12/1/2025
Final Design Review
Design Completion Date
12/1/2025
Design Completion Date
Shop Release
2/2/2026
Shop Release
Production Complete
3/25/2026
Production Complete
Order Close Out
4/2/2026
Order Close Out
Project Wrap Up
4/9/2026
Project Wrap Up
Lessons Learned
4/14/2026
Lessons Learned