Milestone Map: QuoteNo: Q12410 / ProdNo: 1114372


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 1/14/2025 1/14/2025 Initial Quote Receipt & Review
Final Quote Review 6/26/2025 8/12/2025 Final Quote Review Joe Marshall
Contract Review 8/21/2025 Contract Review Frank Edwards
Order Entry 8/21/2025 8/21/2025 Order Entry Frank Edwards
Eng KickOff 8/15/2025 9/2/2025 Eng Kick Off Paul Brown
Financial Review 10/23/2025 Financial Review Frank Edwards
Initial Design Review 8/15/2025 9/9/2025 Initial Design Review Paul Brown
Long Lead Release 8/15/2025 9/18/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 8/15/2025 9/18/2025 Full BOM Release Date
Final Design Review 11/5/2025 Final Design Review Paul Brown
Design Completion Date 8/15/2025 9/18/2025 Design Completion Date
Shop Release 10/20/2025 Shop Release
Production Complete 10/27/2025 Production Complete
Order Close Out 10/29/2025 Order Close Out
Project Wrap Up 10/30/2025 Project Wrap Up
Lessons Learned Lessons Learned