Milestone Map: QuoteNo: Q12410 / ProdNo: 1114372
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
1/14/2025
1/14/2025
Initial Quote Receipt & Review
Final Quote Review
6/26/2025
8/12/2025
Final Quote Review
Joe Marshall
Contract Review
8/21/2025
Contract Review
Frank Edwards
Order Entry
8/21/2025
8/21/2025
Order Entry
Frank Edwards
Eng KickOff
8/15/2025
9/2/2025
Eng Kick Off
Paul Brown
Financial Review
10/23/2025
Financial Review
Frank Edwards
Initial Design Review
8/15/2025
9/9/2025
Initial Design Review
Paul Brown
Long Lead Release
8/15/2025
9/18/2025
Long Lead Release Date
Drawing Package Submittal
Drawing Package Submittal Date
Drawing Package Approval
Drawing Package Approval Date
Full BOM Release
8/15/2025
9/18/2025
Full BOM Release Date
Final Design Review
11/5/2025
Final Design Review
Paul Brown
Design Completion Date
8/15/2025
9/18/2025
Design Completion Date
Shop Release
10/20/2025
Shop Release
Production Complete
10/27/2025
Production Complete
Order Close Out
10/29/2025
Order Close Out
Project Wrap Up
10/30/2025
Project Wrap Up
Lessons Learned
Lessons Learned