Milestone Map: QuoteNo: Q12407 / ProdNo: 1114850


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 6/23/2025 6/23/2025 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 7/1/2025 7/2/2025 Final Quote Review Joe Marshall
Contract Review 9/10/2025 Contract Review Joe Marshall
Order Entry 9/10/2025 9/10/2025 Order Entry Joe Marshall
Eng KickOff 9/12/2025 9/11/2025 Eng Kick Off Scott Tidwell
Financial Review Financial Review
Initial Design Review Initial Design Review
Long Lead Release 9/15/2025 9/11/2025 Long Lead Release Date
Drawing Package Submittal 11/10/2025 Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 9/17/2025 10/10/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 9/18/2025 9/12/2025 Design Completion Date
Shop Release 10/29/2025 Shop Release
Production Complete 12/23/2025 Production Complete
Order Close Out 12/30/2025 Order Close Out
Project Wrap Up 1/7/2026 Project Wrap Up
Lessons Learned Lessons Learned