Milestone Map: QuoteNo: Q12404 / ProdNo: 1112854


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 6/17/2025 6/17/2025 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 6/18/2025 6/18/2025 Final Quote Review Joe Marshall
Contract Review 6/20/2025 6/20/2025 Contract Review Joe Marshall
Order Entry 6/20/2025 6/20/2025 Order Entry Joe Marshall
Eng KickOff 6/25/2025 7/31/2025 Eng Kick Off Joe Marshall
Financial Review 7/23/2025 8/5/2025 Financial Review Frank Edwards
Initial Design Review Initial Design Review
Long Lead Release 6/20/2025 Long Lead Release Date
Drawing Package Submittal 7/16/2025 Drawing Package Submittal Date
Drawing Package Approval 7/18/2025 Drawing Package Approval Date
Full BOM Release 7/18/2025 7/16/2025 Full BOM Release Date
Final Design Review 7/23/2025 8/5/2025 Final Design Review Dylan Smith
Design Completion Date 7/23/2025 8/1/2025 Design Completion Date
Shop Release 8/1/2025 8/12/2025 Shop Release Dylan Smith
Production Complete 8/27/2025 8/27/2025 Production Complete
Order Close Out 8/28/2025 9/24/2025 Order Close Out Noelle Sorano
Project Wrap Up 9/5/2025 9/26/2025 Project Wrap Up
Lessons Learned 9/12/2025 Lessons Learned