Milestone Map: QuoteNo: Q12379 / ProdNo: 1115023
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
5/30/2025
6/3/2025
Initial Quote Receipt & Review
Joe Marshall
Final Quote Review
6/2/2025
6/25/2025
Final Quote Review
Joe Marshall
Contract Review
9/18/2025
Contract Review
Joe Marshall
Order Entry
9/15/2025
9/18/2025
Order Entry
Joe Marshall
Eng KickOff
9/19/2025
9/26/2025
Eng Kick Off
Joe Marshall
Financial Review
Financial Review
Initial Design Review
9/29/2025
Initial Design Review
Scott Tidwell
Long Lead Release
9/23/2025
9/29/2025
Long Lead Release Date
Drawing Package Submittal
10/7/2025
9/30/2025
Drawing Package Submittal Date
Drawing Package Approval
10/10/2025
10/3/2025
Drawing Package Approval Date
Full BOM Release
10/10/2025
10/10/2025
Full BOM Release Date
Final Design Review
10/14/2025
10/17/2025
Final Design Review
Joe Marshall
Design Completion Date
10/15/2025
11/10/2025
Design Completion Date
Shop Release
11/21/2025
Shop Release
Production Complete
1/6/2026
Production Complete
Order Close Out
1/8/2026
Order Close Out
Project Wrap Up
1/16/2026
Project Wrap Up
Lessons Learned
Lessons Learned