Milestone Map: QuoteNo: Q11982 / ProdNo: 1108587


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 6/6/2024 6/6/2024 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 6/10/2024 12/17/2024 Final Quote Review Joe Marshall
Contract Review 12/20/2024 Contract Review Joe Marshall
Order Entry 12/20/2024 12/20/2024 Order Entry Joe Marshall
Eng KickOff 12/24/2024 1/8/2025 Eng Kick Off
Financial Review 1/9/2025 2/27/2025 Financial Review
Initial Design Review 1/10/2025 1/30/2025 Initial Design Review
Long Lead Release 1/14/2025 1/14/2025 Long Lead Release Date
Drawing Package Submittal 2/25/2025 2/25/2025 Drawing Package Submittal Date
Drawing Package Approval 3/1/2025 3/1/2025 Drawing Package Approval Date
Full BOM Release 2/26/2025 2/26/2025 Full BOM Release Date
Final Design Review 2/24/2025 2/26/2025 Final Design Review
Design Completion Date 2/28/2025 2/26/2025 Design Completion Date
Shop Release 4/14/2024 3/19/2025 Shop Release
Production Complete 5/2/2025 Production Complete
Order Close Out 5/6/2025 9/24/2025 Order Close Out Noelle Sorano
Project Wrap Up 5/23/2025 9/26/2025 Project Wrap Up
Lessons Learned Lessons Learned