Milestone Map: QuoteNo: Q11913 / ProdNo: 1103722


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review Initial Quote Receipt & Review
Final Quote Review Final Quote Review
Contract Review Contract Review
Order Entry Order Entry
Eng KickOff 5/14/2024 5/7/2024 Eng Kick Off
Financial Review 5/8/2024 5/8/2024 Financial Review
Initial Design Review 5/17/2024 5/17/2024 Initial Design Review
Long Lead Release Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release Full BOM Release Date
Final Design Review 5/24/2024 6/4/2024 Final Design Review
Design Completion Date Design Completion Date
Shop Release 6/14/2024 7/8/2024 Shop Release
Production Complete Production Complete
Order Close Out Order Close Out
Project Wrap Up Project Wrap Up
Lessons Learned Lessons Learned