Milestone Map: QuoteNo: Q12295 / ProdNo: 1111968


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review Initial Quote Receipt & Review
Final Quote Review Final Quote Review
Contract Review Contract Review
Order Entry Order Entry
Eng KickOff 5/15/2025 5/15/2025 Eng Kick Off
Financial Review Financial Review
Initial Design Review 6/16/2025 8/11/2025 Initial Design Review Scott Tidwell
Long Lead Release 5/15/2025 Long Lead Release Date
Drawing Package Submittal 6/12/2025 Drawing Package Submittal Date
Drawing Package Approval 6/13/2025 Drawing Package Approval Date
Full BOM Release 8/11/2025 Full BOM Release Date
Final Design Review 6/13/2025 6/13/2025 Final Design Review Joe Marshall
Design Completion Date Design Completion Date
Shop Release 8/4/2025 9/11/2025 Shop Release Scott Tidwell
Production Complete Production Complete
Order Close Out Order Close Out
Project Wrap Up Project Wrap Up