Milestone Map: QuoteNo: Q12363 / ProdNo: 1111916


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 5/8/2025 5/8/2025 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 5/8/2025 5/8/2025 Final Quote Review Joe Marshall
Contract Review 5/12/2025 Contract Review Joe Marshall
Order Entry 5/12/2025 5/12/2025 Order Entry Joe Marshall
Eng KickOff 5/12/2025 5/21/2025 Eng Kick Off Kyle Swindlehurst
Financial Review 5/12/2025 5/12/2025 Financial Review
Initial Design Review Initial Design Review
Long Lead Release 5/12/2025 5/12/2025 Long Lead Release Date
Drawing Package Submittal 5/30/2025 5/30/2025 Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 5/12/2025 5/12/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 5/16/2025 5/12/2025 Design Completion Date
Shop Release 7/14/2025 6/10/2025 Shop Release Dylan Smith
Production Complete 6/19/2025 6/27/2025 Production Complete
Order Close Out 6/23/2025 Order Close Out
Project Wrap Up 7/2/2025 Project Wrap Up
Lessons Learned Lessons Learned