Milestone Map: QuoteNo: 12022 / ProdNo: 1111884


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 4/21/2025 4/21/2025 Initial Quote Receipt & Review
Final Quote Review 4/24/2025 4/24/2025 Final Quote Review Stephen English
Contract Review 5/10/2025 5/10/2025 Contract Review Stephen English
Order Entry 5/7/2025 5/7/2025 Order Entry
Eng KickOff 5/15/2025 5/15/2025 Eng Kick Off Paul Brown
Financial Review 5/30/2025 Financial Review
Initial Design Review 5/26/2025 5/27/2025 Initial Design Review Paul Brown
Long Lead Release 5/23/2025 5/21/2025 Long Lead Release Date
Drawing Package Submittal 6/13/2025 Drawing Package Submittal Date
Drawing Package Approval 7/24/2025 7/24/2025 Drawing Package Approval Date
Full BOM Release 6/6/2025 5/21/2025 Full BOM Release Date
Final Design Review 6/5/2025 6/5/2025 Final Design Review Paul Brown
Design Completion Date 6/6/2025 7/17/2025 Design Completion Date
Shop Release 8/11/2025 8/7/2025 Shop Release Paul Brown
Production Complete Production Complete
Order Close Out Order Close Out
Project Wrap Up Project Wrap Up
Lessons Learned Lessons Learned