Milestone Map: QuoteNo: 12017 / ProdNo: 1111656


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 6/7/2024 6/7/2024 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 6/10/2024 6/12/2024 Final Quote Review Joe Marshall
Contract Review 5/2/2025 Contract Review Joe Marshall
Order Entry 5/2/2025 5/2/2025 Order Entry Joe Marshall
Eng KickOff 5/6/2025 5/5/2025 Eng Kick Off
Financial Review 5/2/2025 5/2/2025 Financial Review
Initial Design Review 5/7/2025 Initial Design Review
Long Lead Release 5/2/2025 Long Lead Release Date
Drawing Package Submittal 5/22/2025 Drawing Package Submittal Date
Drawing Package Approval 5/23/2025 Drawing Package Approval Date
Full BOM Release 5/30/2025 5/2/2025 Full BOM Release Date
Final Design Review 6/2/2025 5/7/2025 Final Design Review
Design Completion Date 5/9/2025 5/9/2025 Design Completion Date
Shop Release 7/28/2025 7/30/2025 Shop Release Dylan Smith
Production Complete 8/13/2025 9/11/2025 Production Complete
Order Close Out 8/15/2025 9/24/2025 Order Close Out Noelle Sorano
Project Wrap Up 8/22/2025 9/26/2025 Project Wrap Up
Lessons Learned 8/29/2025 Lessons Learned