Milestone Map: QuoteNo: 12016 / ProdNo: 1111552


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 4/21/2025 4/21/2025 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 4/24/2025 4/25/2025 Final Quote Review Joe Marshall
Contract Review Contract Review Joe Marshall
Order Entry 5/7/2025 5/7/2025 Order Entry Joe Marshall
Eng KickOff 5/7/2025 8/5/2025 Eng Kick Off Scott Tidwell
Financial Review Financial Review
Initial Design Review 8/29/2025 Initial Design Review Scott Tidwell
Long Lead Release 4/29/2025 Long Lead Release Date
Drawing Package Submittal 4/29/2025 Drawing Package Submittal Date
Drawing Package Approval 5/13/2025 Drawing Package Approval Date
Full BOM Release 5/9/2025 5/13/2025 Full BOM Release Date
Final Design Review Final Design Review
Design Completion Date 5/9/2025 5/13/2025 Design Completion Date
Shop Release 5/19/2025 8/29/2025 Shop Release Scott Tidwell
Production Complete 5/27/2025 Production Complete
Order Close Out 5/28/2025 Order Close Out
Project Wrap Up 6/6/2025 Project Wrap Up
Lessons Learned 6/13/2025 Lessons Learned