Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
2/24/2025
2/25/2025
Initial Quote Receipt & Review
Joe Marshall
Final Quote Review
2/26/2025
4/14/2025
Final Quote Review
Joe Marshall
Contract Review
4/25/2025
Contract Review
Joe Marshall
Order Entry
4/28/2025
4/25/2025
Order Entry
Joe Marshall
Eng KickOff
4/29/2025
4/29/2025
Eng Kick Off
Financial Review
5/9/2025
4/25/2025
Financial Review
Initial Design Review
5/9/2025
5/8/2025
Initial Design Review
Dylan Smith
Long Lead Release
4/25/2025
4/25/2025
Long Lead Release Date
Drawing Package Submittal
Drawing Package Submittal Date
Drawing Package Approval
Drawing Package Approval Date
Full BOM Release
5/2/2025
5/7/2025
Full BOM Release Date
Final Design Review
5/9/2025
5/12/2025
Final Design Review
Dylan Smith
Design Completion Date
5/16/2025
8/20/2025
Design Completion Date
Shop Release
6/2/2025
6/6/2025
Shop Release
Dylan Smith
Production Complete
6/19/2025
8/1/2025
Production Complete
Order Close Out
6/23/2025
9/24/2025
Order Close Out
Noelle Sorano
Project Wrap Up
6/27/2025
9/26/2025
Project Wrap Up
Lessons Learned
7/11/2025
Lessons Learned