Milestone Map: QuoteNo: 12014 / ProdNo: 1111024


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review 2/12/2025 2/12/2025 Initial Quote Receipt & Review Joe Marshall
Final Quote Review 2/19/2025 3/14/2025 Final Quote Review Joe Marshall
Contract Review 4/3/2025 Contract Review Joe Marshall
Order Entry 4/3/2025 4/3/2025 Order Entry Joe Marshall
Eng KickOff 4/8/2025 4/8/2025 Eng Kick Off
Financial Review Financial Review
Initial Design Review Initial Design Review
Long Lead Release 4/4/2025 4/4/2025 Long Lead Release Date
Drawing Package Submittal Drawing Package Submittal Date
Drawing Package Approval Drawing Package Approval Date
Full BOM Release 5/1/2025 5/1/2025 Full BOM Release Date
Final Design Review 5/2/2025 5/2/2025 Final Design Review
Design Completion Date 5/7/2025 5/2/2025 Design Completion Date
Shop Release 6/2/2025 6/9/2025 Shop Release Dylan Smith
Production Complete 6/12/2025 Production Complete
Order Close Out 6/16/2025 Order Close Out
Project Wrap Up 6/27/2025 Project Wrap Up
Lessons Learned Lessons Learned