Milestone Map: QuoteNo: 12012 / ProdNo: 1111019
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
2/12/2025
2/12/2025
Initial Quote Receipt & Review
Joe Marshall
Final Quote Review
2/19/2025
3/14/2025
Final Quote Review
Joe Marshall
Contract Review
4/3/2025
Contract Review
Joe Marshall
Order Entry
4/3/2025
4/3/2025
Order Entry
Joe Marshall
Eng KickOff
4/8/2025
4/8/2025
Eng Kick Off
Financial Review
Financial Review
Initial Design Review
Initial Design Review
Long Lead Release
4/4/2025
4/4/2025
Long Lead Release Date
Drawing Package Submittal
Drawing Package Submittal Date
Drawing Package Approval
Drawing Package Approval Date
Full BOM Release
5/1/2025
5/1/2025
Full BOM Release Date
Final Design Review
5/2/2025
5/2/2025
Final Design Review
Design Completion Date
5/7/2025
5/1/2025
Design Completion Date
Shop Release
6/2/2025
6/9/2025
Shop Release
Dylan Smith
Production Complete
6/12/2025
Production Complete
Order Close Out
6/16/2025
Order Close Out
Project Wrap Up
6/27/2025
Project Wrap Up
Lessons Learned
Lessons Learned