Milestone Map: QuoteNo: 12008 / ProdNo: 1110996
Milestone
MilestoneDue
MilestoneCompleted
Form Link
Completed By
Initial Quote Receipt & Review
2/4/2025
2/3/2025
Initial Quote Receipt & Review
Joe Marshall
Final Quote Review
2/7/2025
2/3/2025
Final Quote Review
Joe Marshall
Contract Review
Contract Review
Joe Marshall
Order Entry
3/14/2025
3/13/2025
Order Entry
Joe Marshall
Eng KickOff
3/17/2025
8/5/2025
Eng Kick Off
Scott Tidwell
Financial Review
Financial Review
Initial Design Review
8/29/2025
Initial Design Review
Scott Tidwell
Long Lead Release
4/29/2025
Long Lead Release Date
Drawing Package Submittal
4/29/2025
Drawing Package Submittal Date
Drawing Package Approval
5/13/2025
Drawing Package Approval Date
Full BOM Release
3/26/2025
5/13/2025
Full BOM Release Date
Final Design Review
Final Design Review
Design Completion Date
3/28/2025
5/13/2025
Design Completion Date
Shop Release
4/25/2025
5/29/2025
Shop Release
Production Complete
5/15/2025
Production Complete
Order Close Out
5/19/2025
Order Close Out
Project Wrap Up
5/30/2025
Project Wrap Up
Lessons Learned
6/6/2025
Lessons Learned