Milestone Map: QuoteNo: 12006 / ProdNo: 1110937


Milestone MilestoneDue MilestoneCompleted Form Link Completed By
Initial Quote Receipt & Review Initial Quote Receipt & Review
Final Quote Review Final Quote Review
Contract Review Contract Review
Order Entry Order Entry
Eng KickOff 4/11/2025 4/11/2025 Eng Kick Off
Financial Review 4/18/2025 Financial Review
Initial Design Review 4/30/2025 8/29/2025 Initial Design Review Scott Tidwell
Long Lead Release 4/10/2025 Long Lead Release Date
Drawing Package Submittal 5/6/2025 Drawing Package Submittal Date
Drawing Package Approval 6/10/2025 Drawing Package Approval Date
Full BOM Release 5/12/2025 Full BOM Release Date
Final Design Review 5/9/2025 Final Design Review
Design Completion Date 5/12/2025 Design Completion Date
Shop Release 6/13/2025 9/18/2025 Shop Release Joe Marshall
Production Complete 10/29/2025 Production Complete
Order Close Out Order Close Out
Project Wrap Up Project Wrap Up
Lessons Learned Lessons Learned